SIScheduleInsight SAMPLE REPORT ← Back Analyze your schedule free
ScheduleInsight · Schedule Health Report

Tower C — Programme R12

Prepared for: PMO / Owner's representative  ·  Generated: 14 Mar 2026
Data date: 28 Feb 2026  ·  Forecast finish: 19 Nov 2027  ·  3,842 activities  ·  9,610 logic links  ·  Baseline: R10 (attached)

Executive summary

73
SQI

Schedule Quality Index — 73 / 100 · below the 75 healthy threshold

Weighted across 14 DCMA-aligned checks. Down 4 points vs the R10 baseline, driven mainly by open-ended logic and constraint usage in the structural steel scope.

3 failing4 warning7 healthy
3,842
Activities
12%
Critical
17
Negative float
5%
Open ends
2.5
Logic density

DCMA metric breakdown

#CheckValueTargetResult
1Missing logic (open ends)5.0%<5%WARN
2Logic density2.52.0–3.5PASS
3Finish-to-start relationships86%>80%PASS
4Lags3.1%<5%PASS
5Leads (negative lags)6ZeroFAIL
6Out of sequence11ZeroWARN
7Negative float17ZeroFAIL
8High float (>50d)9.4%<10%PASS
9Critical path %12%<15%PASS
10CPLI0.94≥1.0WARN
11High duration (>44d)4.2%<5%PASS
12Hard constraints3.1%<2%FAIL
13Soft constraints4.4%<5%PASS
14BEI (baseline execution index)0.91≥1.0WARN

Critical findings — activities driving the score

Activity IDNameIssueBaselineCurrentSlip
A1422Erect columns Grid G, L4–6Negative float10 Jul 2728 Jul 27+18d
A1733Pre-pour inspection, Level 3Hard constraint02 Aug 2714 Aug 27+12d
A1801MEP rough-in, Zone AOpen end19 Aug 2726 Aug 27+7d
A2104Curtain wall install, NorthNegative lag03 Sep 2709 Sep 27+6d
A2240Lift core handoverOut of sequence21 Sep 2725 Sep 27+4d

Plain-language narrative

The programme scores 73/100, four points below the previous revision and under the 75 healthy threshold. The decline is concentrated in the structural steel scope, where 17 activities now carry negative float — most critically A1422 · Erect columns Grid G, which has slipped 18 days against the R10 baseline and is driving the longest path. Three activities have been re-anchored with hard constraints (above the 2% target), which masks true float and should be replaced with logic where the sequencing is genuine. Open-ended logic sits at exactly 5%, on the warning boundary; closing the successor links on the MEP rough-in chain (A1801 and its siblings) would recover both the open-ends and out-of-sequence checks. Net effect on the forecast finish is a +18 day slip to 19 Nov 2027, recoverable with constraint cleanup and resequencing of the Grid G erection. Every figure in this narrative is traced to the activities listed above.

This took one upload and about eight minutes.

Load your own P6 schedule, explore every metric free, and generate the same report when you need it.