The programme meets the minimum acceptance score and can be received into the record, but it carries conditions the contractor must resolve in the next revision. It is not rejected, and it is not accepted clean. The specific conditions are listed below.
| # | Check | Measured | Requirement | Result |
|---|---|---|---|---|
| 1 | Missing logic (open ends) | 5.0% | <5% | WARN |
| 2 | Logic density | 2.5 | 2.0–3.5 | PASS |
| 3 | Finish-to-start relationships | 86% | >80% | PASS |
| 4 | Lags | 3.1% | <5% | PASS |
| 5 | Leads (negative lags) | 6 | Zero | FAIL |
| 6 | Out of sequence | 11 | Zero | WARN |
| 7 | Negative float | 17 | Zero | FAIL |
| 8 | Near-critical (float ≤10d) | 8.2% | <10% | PASS |
| 9 | High float (>44d) | 9.4% | <10% | PASS |
| 10 | Critical path test | 12% | <15% | PASS |
| 11 | CPLI | 0.94 | ≥1.0 | WARN |
| 12 | High duration (>44d) | 4.2% | <5% | PASS |
| 13 | Insufficient detail | 3.8% | <5% | PASS |
| 14 | Hard constraints | 3.1% | <2% | FAIL |
| 15 | Soft constraints | 4.4% | <5% | PASS |
| 16 | Milestone coverage | 2.6% | >2% | PASS |
| 17 | BEI (baseline execution index) | 0.91 | ≥1.0 | WARN |
| 18 | SPI (schedule performance index) | 0.93 | ≥1.0 | WARN |
The five warnings (open ends at the 5% boundary, out-of-sequence progress, CPLI, BEI and SPI all below 1.0) are noted but do not by themselves prevent acceptance under the configured rule. They are early indicators of schedule pressure and should be watched in the trend review rather than treated as resubmission blockers.
Acceptance gate. The scorecard applies the organisation's configured acceptance rule to the 18-point schedule-quality assessment (the DCMA 14-point checks plus four supplementary indices). The verdict is one of ACCEPT, ACCEPT WITH COMMENTS, or REJECT, determined by the score threshold and the permitted number of failed and warning checks.
Configurable thresholds. The minimum score, maximum failed checks and maximum warnings shown here are defaults; each organisation sets its own on the Criteria tab so the gate reflects its acceptance standard rather than a generic one.
Decision support, not certification. This scorecard is an aid to the acceptance decision. The reviewing party remains responsible for accepting, conditionally accepting, or rejecting the submission; it is not a contractual determination.